The Ishikawa
Diagram (Page 2 of 2)
The Ishikawa
Diagram is usually constructed by the problem-solving team using the
following basic steps:
1)
prepare the basic framework of the Ishikawa Diagram on a large
writing area, such as a whiteboard or a flipchart;
See Also:
2) define the problem
that needs to be addressed and describe it in clear and specific terms,
then write this description in the problem box or fish head of the
diagram;
3) finalize the cause
categories of the major branches and write these at the tips of the
major branches; if the members are all new to the Ishikawa Diagram and
can't decide on which categories to write, use the 4 M's as categories;
4)
conduct the
brainstorming
session
using these basic brainstorming guidelines:
a) each
participant will be asked one at a time to give a cause of the problem
(only one input per turn!), saying 'Pass' if he or she can't think of
any during his or her turn;
b) each cause
identified will be 'hung' on the major branch of the category it belongs
to; if it's the cause of another cause that's already on the diagram,
then it must be 'hung' on the branch of the latter; if applicable, a
cause may be placed on several branches;
c) the
brainstorming session will continue until everyone says 'Pass'.
5) interpret
the Ishikawa Diagram once it's finished.
There are
many ways to interpret the Ishikawa Diagram. The fastest and
simplest way to do it is for the group to choose the top five causes on
the diagram and rank them, using their collective knowledge and any data
available. The selection of the major causes may be done by voting
or any other process that allows the group to agree on the ranking.
The selected causes are then encircled on the diagram, with their ranks
written beside them. The team may then investigate these causes
further and use problem-solving techniques to eliminate their
occurrences.
Figure 2.
Example of a simple but finished Ishikawa Diagram
Copyright
©
2001-2005
www.SemiconFarEast.com.
All Rights Reserved. |
||