| Is there such thing as test escapee? Can a unit really escaped from being tested? |
|
| Back to top |
|
| Tagatest |
|
Guest
|
| Posted: Wed Dec 21, 2025 11:46 am Post subject: |
| |
The term 'test escapee' usually refers to a reject whose failure mode can not be detected by the existing test program. So it's really more of a test program inadequacy issue than the unit pulling off a Houdini act on the tester.  |
|
| Back to top |
|
| pan-gulo |
|
Guest
|
| Posted: Thu Dec 22, 2025 6:54 am Post subject: |
| |
Yes, test escapee usually refers to (1) test program inadequacy and (2) mistest or misprocessing such as mixing of reject with the good (human/operator error).
Bakit nga ba nag-stuck yung term na "test escapee" dito sa mga event na ito when in fact it is not? |
|
| Back to top |
|
| Asmoth |
|
Joined: 31 Aug 2026 Posts: 16
|
| Posted: Thu Dec 22, 2025 3:55 pm Post subject: |
| |
Test escapee refers to a scenario wherein a "valid" reject on a certain parameter, passed the test of that parameter. Examples for these are:
1. Consider a test that measures the DUT's(device under test) output at a certain resistance load condition. Usually, test programmers uses a relay to connect/disconnect the load to/from the DUT's ouput. Now if a valid reject(with load) part is tested, and assuming that the relay got stuck, meaning that the load was not connected to the output when the output was measured, there's a big chance that this part will passed this test, since it has no load. Resulting to a test escapee scenario.
2. Another example is ineffective(inadequate) guardband generation. Consider a valid reject part but marginal. If this part will be tested at production(tighter limits), there's a chance that this part will fall within the PD limits, if the guardband is inadequate, hence, passing the test, resulting to a test escapee. This the reason why guardband generation is a very critical process. An effective guardband will ensure that:
a. a valid reject will not fall within the production limits, and therefore will screen out(fail) this part.
b. good parts passing the PD limits, will also passed QC limits during QA sampling.
"Test escapee" are sometime mis-interpreted as "test coverage", or vice versa. Note that "test coverage" refers to a valid failure mode of the part, but this failure mode is NOT tested by the existing test program. Hence, this failing part will passed the test program and will be considered good. _________________ Asmoth72 |
|
| Back to top |
|
| Guest |
|
|
| Posted: Wed Dec 28, 2025 10:54 am Post subject: |
| |
This falls on test program inadequacy. The unit underwent test, hence not a "test escapee".
| Asmoth wrote: | Test escapee refers to a scenario wherein a "valid" reject on a certain parameter, passed the test of that parameter. Examples for these are:
1. Consider a test that measures the DUT's(device under test) output at a certain resistance load condition. Usually, test programmers uses a relay to connect/disconnect the load to/from the DUT's ouput. Now if a valid reject(with load) part is tested, and assuming that the relay got stuck, meaning that the load was not connected to the output when the output was measured, there's a big chance that this part will passed this test, since it has no load. Resulting to a test escapee scenario.
2. Another example is ineffective(inadequate) guardband generation. Consider a valid reject part but marginal. If this part will be tested at production(tighter limits), there's a chance that this part will fall within the PD limits, if the guardband is inadequate, hence, passing the test, resulting to a test escapee. This the reason why guardband generation is a very critical process. An effective guardband will ensure that:
a. a valid reject will not fall within the production limits, and therefore will screen out(fail) this part.
b. good parts passing the PD limits, will also passed QC limits during QA sampling.
"Test escapee" are sometime mis-interpreted as "test coverage", or vice versa. Note that "test coverage" refers to a valid failure mode of the part, but this failure mode is NOT tested by the existing test program. Hence, this failing part will passed the test program and will be considered good. |
|
|
| Back to top |
|
| Asmoth |
|
Joined: 31 Aug 2026 Posts: 16
|
| Posted: Wed Dec 28, 2025 12:11 pm Post subject: |
| |
Hi Guest,
I think we(our company) have a different definition on the same term("test escapee").
In our company, we defined test escapee as a case of a valid failing parts passing the ATE test. The part got tested(but passed) on that particular failure mode.
My personal interpretation of test program inadequacy is that it doesn't have sufficient test to cover all the failure modes of the part, eventhough it covers all the datasheet specs, hence the term inadequacy(inadequate, insufficient, not enough). This means the part was NOT tested on that particular failure mode. In my own experience, there are failure modes that were raised by our customers. They experience these failure modes in their applications, which we did not encountered at our end. Hence, we develop a "screen" test to filter out these type of failing parts during ATE test. In our company, this case falls as "test coverage" issue. Meaning, the failure mode was not filtered out by the existing test program since it was NOT tested. _________________ Asmoth72 |
|
| Back to top |
|
| Guest Who |
|
Guest
|
| Posted: Wed Dec 28, 2025 12:49 pm Post subject: |
| |
| I actually don't use the term test escapee, as I believe there is no such thing. Units can't escape from being tested. |
|
| Back to top |
|
| Asmoth |
|
Joined: 31 Aug 2026 Posts: 16
|
| Posted: Wed Dec 28, 2025 2:18 pm Post subject: |
| |
I agree, units can't escape from being tested(unless we have a mixing issue), but there are cases that a valid failing part on a certain parameter can pass the test on that parameter for some reasons(ie. as describe in my two previous examples). _________________ Asmoth72 |
|
| Back to top |
|
| Pan-gulo |
|
Guest
|
| Posted: Thu Dec 29, 2025 7:39 am Post subject: |
| |
That part was tested hence not a test escapee. Here is a known reject device but you tested or binned it good, does the part hide its failure. NO!
Scenario:
Problem - customer complaint ...
Root cause - test escapee
Corrective - revise/add/modify/enhance/etc. test program
It seems that the root cause and the corrective action are not interconnected. How can you arrive to a good corrective action when you define the root cause incorrectly or poorly. |
|
| Back to top |
|
| Asmoth |
|
Joined: 31 Aug 2026 Posts: 16
|
| Posted: Thu Dec 29, 2025 9:17 am Post subject: |
| |
Pan-gulo,
It appears that you're a bit confuse on the "customer complaint" example I've discussed. Please note that this example was presented for the "test coverage" category(or "test program inadequacy" to some companies), and not "test escapee" as you've mentioned.
I think the scenario would look more clearly as shown below:
Scenario:
Problem - customer complaint on a certain failure mode, that is not catch by the existing program, since this failure mode is not tested by the current test program. This failure mode was encountered by the customer, but not on our side.
Root cause - test coverage, test inadequacy(or whatever more preferrable)
Corrective - revise/add/modify/enhance/etc. test program
I think with this presentation, the root cause and the Corrective action is now interconnected.
As mentioned previously, different semicon companies have different definition on the term "test escapee". _________________ Asmoth72 |
|
| Back to top |
|
| Asmoth |
|
Joined: 31 Aug 2026 Posts: 16
|
| Posted: Thu Dec 29, 2025 9:36 am Post subject: |
| |
For this query,
| Pan-gulo wrote: | That part was tested hence not a test escapee. Here is a known reject device but you tested or binned it good, does the part hide its failure. NO!
|
Please refer to the example below:
| Asmoth wrote: |
1. Consider a test that measures the DUT's(device under test) output at a certain resistance load condition. Usually, test programmers uses a relay to connect/disconnect the load to/from the DUT's ouput. Now if a valid reject(with load) part is tested, and assuming that the relay got stuck, meaning that the load was not connected to the output when the output was measured, there's a big chance that this part will passed this test, since it has no load. Resulting to a test escapee scenario.
|
Does the part hide its failure?
I think the appropriate answer would be that "the test program was not able to catch this failure".
Can this be categorize as "test program inadequacy"?
I don't think so. How can it be a case of "test program inadequacy" when in fact, the part was tested on this parameter. _________________ Asmoth72 |
|
| Back to top |
|
| lbrtmghs |
|
Joined: 22 Mar 2026 Posts: 1
|
| Posted: Wed Mar 22, 2026 8:22 am Post subject: Re: Test escapee |
| |
| Anonymous wrote: | | Is there such thing as test escapee? Can a unit really escaped from being tested? |
Yes there is. As an equipment engineer for several years, i've seen a few cases of test escapees, of coure all equipment related issue. Take for example a gravity feed test handler encountering poor singulation prior test site. Some test handlers are equiped with a double drop sensor to detect a "double drop" event at test site, but some don't. For those handlers without this error-proofing feature, test escapee is potential to happen. When the singulator fails to function properly. Can it be detected after summary reconciliation? Yes and No. Yes, if the lot testing has no interruption, no maintenance intervention which could result to test lot summary discrepancy. When a an untested unit mixed with a good bin, operator should see an excess actual unit count vs the printed summary. But sometimes NO. It is normal for some setup to be interrupted during lot processing specially when an O/R occurs. If the technician failed to instruct the operator to do partial summary, any testing done by him will add to the lot summary making it difficult to determine if there is an occurrence of test escapee- summary reconciliation fails to detect such occurence. This is almost true in a single pass testing. Sometimes in-line-sampling can't even capture a test escapee (due to sample lot sizing).
Other handlers have software bugs which can only be detected if the machine is set to worst setup condition. |
|
| Back to top |
|
| Choose Display Order |
|
| User Permissions |
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum
|
Skin Created by: Sigma12 Powered by phpBB © 2001, 2002 phpBB Group
|
|